Dredging Works Planning 2025–2026
This year, dredging works will once again take place in our marina to ensure that all boats can navigate safely at all times.
This means that most boats will need to move this winter. The catways will then be removed, dredged, and reinstalled. Boats will be able to return afterwards.
Below is the initial schedule, which may be subject to change (weather conditions, technical challenges, etc.).
We will keep you informed throughout the duration of the works.

- Complete clearance of pontoons H (even and odd) and I (odd)
Partial clearance between I (even) and J (odd), and between J (even) and K (odd)
Move before: 10/11/2025
Return possible from: 08/12/2025 - Complete clearance between pontoons M (even) and N (odd), and N (even) and O (odd)
Partial clearance between K (even) and L (odd), and between L (even) and M (odd)
Move before: 17/11/2025
Return possible from: 12/01/2026 - Boats on pontoons C-NORTH (only even-numbered C), D, E, F, G:
Move before: 15/12/2025
Return possible from: 09/02/2026 - Boats on pontoons Ab, A, B, C-SOUTH (only odd-numbered C):
Move before: 14/01/2026
Return possible from: 23/02/2026
Does your boat need to move this winter?
Please contact us as soon as you know when you can move your boat — we will provide you with a temporary berth.
Check the dates above carefully and make sure to move on time. Also, please return to your permanent berth as soon as it becomes available again.
Thank you in advance for your cooperation