Dredging Works Planning 2026–2027
This year, dredging works will once again take place in our marina to ensure that all boats can navigate safely at all times.
This means that most boats will need to move this winter. The catways will then be removed, dredged, and reinstalled. Boats will be able to return afterwards.
Below is the initial schedule, which may be subject to change (weather conditions, technical challenges, etc.).
We will keep you informed throughout the duration of the works.

- ZONE 1
Completely clear pontoons N-South, O, P, Q, R, S, T and U
Move before 18 November
Return to the berth possible from 18 January - ZONE 2
Completely clear between I-South, J, K, L, M-North
Head piers H-South, I, J, K, L, M, N-North
Move before 7 December
Return to the berth possible from 25 January - ZONE 3
Boats on pontoons C-North, C-STORM WALL, D, E, F, G
Move before 18 January
Return to the berth possible from 1 March - ZONE 4
Boats on pontoons Ab, A, B, C-South
Move before 29 January
Return to the berth possible from 3 March
Does your boat need to move this winter?
Please contact us as soon as you know when you can move your boat — we will provide you with a temporary berth.
Check the dates above carefully and make sure to move on time. Also, please return to your permanent berth as soon as it becomes available again.
Thank you in advance for your cooperation